Prioritized programming tasks 2009
- DONE Incorporate Ben's changes to make it easier to modify HTML in pages using style sheets and get consistency across all pages.
- Estimated Time: 2 days ? - plus lots of effort from Ben
- Updates to web page HTML, logos, etc
- Estimated Time: Completed by Ben? Or still more to do? Some requests still outstanding in issue tracker.
- DONE Revert to a single AVH home page rather than separate URLs for public and restricted interfaces.
- Estimated Time: 1 day
- DONE Several changes to code to pull out hard-coded parameters into properties that can be easily modified in a configuration file - this was requested by NZVH but was a good thing to do anyway
- Estimated Time: 2 days
- DONE Other changes requested by NZVH to enable them to use AVH code
- Estimated Time: 1 day
- DONE Write program to directly query AVH database for queries that generate larger responses than can currently be handled by web interface (> 100K records) and output results in CSV, do queries requested by David Cantrill and return CD of results to MELB
- Estimated Time: 3 days
- DONE Change user interface and output page format for simple query based on Niels' javascript
- Estimated Time: 2 days
- Fix problems with Niels' javascript overriding HTML styles
- Estimated Time: ? - Niels to work on
- Change user interface and output page format for extended query based on Niels' javascript
- Estimated Time: 5 days, once Niels has completed fixes to the Javascript
- Modify code for registration of users to allow approval by herbarium representatives
- Estimated Time: 4 days - mostly done, 2 more days to do some final changes, testing and documentation
- Program to parse data dumps in HISPID3 CSV format and ingest into AVH database, documentation of requirements for data dumps
- Estimated Time: 20 days - mostly done, 1 more day needed
- Web interface to enable herbarium administrators to upload CSV file data dumps, and automated ingest into AVH database - without requiring AVH to be offline during the ingest
- Estimated Time: 12 days - mostly done, a few more days needed
- Check ingest of new data dumps into AVH database
- Estimated Time: 1 day
- Project planning and meetings
- Estimated Time: 4 days
Additional tasks
- Synchronize between multiple instances of AVH database
- Estimated Time: 3 days - have trialled it, needs to be documented and some more testing
- API for simple query
- Estimated Time: Several days - initial attempt introduced bugs, not yet clear how much longer it will take to complete
- Integrate BioCASE or TAPIR feeds from WA, TAS, NT and CANB ?
- Estimated Time: a few weeks, possibly more. To be funded by ALA
- Add Rex Croft's Google Maps interface, either as an option or a replacement to current mapper ?
- Estimated Time: several days for eRSA, plus a few days of Rex's time
- BioCASE provider from AVH database
- Estimated Time: a couple of weeks. To be funded by ALA